CIPAA 2012 : Section 30 Direct Payment – Timing of Notice and “Money Due or Payable”
Tri Pacific Engineering Sdn Bhd v KL Eco City Sdn Bhd [W-02-(C)(A)-1102-07/2024]
What happens if the notice for direct payment is issued before the time for payment under the adjudication decision has expired? Further, how should the Court determine whether the
CIPAA 2012: Is Retention Sum “Money Due or Payable” by the Principal Post-Termination of the Main Contractor?
Kinu Sdn Bhd v Kerajaan Malaysia (Jabatan Kerja Raya Malaysia) [W-01(C)(A)-523-08/2024]
Section 30 of the Construction Industry Payment and Adjudication Act 2012 (“CIPAA 2012”) enables a subcontractor to request direct payment from the principal or employer if the
CIPAA 2012 : Prohibition of Conditional Payment Clause extends beyond Adjudication Proceedings?
SPM Energy Sdn Bhd & Anor v Multi Discovery Sdn Bhd [B-02(NCvC)(W)-1669-09/2022]
CIPAA 2012 : Prohibition of Conditional Payment Clause extends beyond Adjudication Proceedings? SPM ENERGY SDN BHD & ANOR V MULTI DISCOVERY SDN BHD [B02(NCVC)(W)-1669-09/2022]
CIPAA 2012 : Examining the Limits of Cross-Claims in Adjudication
Tera VA Sdn Bhd v Ayam Bintang Istimewa Sdn Bhd [B-02(C)(A)-1948-11/2023 & B-02(C)(A)-1949-11/2023]
CIPAA 2012 : Examining the Limits of Cross Claims in Adjudication TERA VA SDN BHD V AYAM BINTANG ISTIMEWA SDN BHD [B-02(C)(A)-1948 11/2023 & B-02(C)(A)-1949-11/2023] ISSUES It
CIPAA 2012 : CIPAA Claims Against A Sole Proprietor
Hongler Enterprise Sdn Bhd v Chai Hon Sang (trading as Hock Seng Trading & Construction) [WA-24C-130-08/2023]
CIPAA 2012 : CIPAA Claims Against A Sole Proprietor HONGLER ENTERPRISE SDN BHD V CHAI HON SANG (TRADING AS HOCK SENG TRADING & CONSTRUCTION) [WA-24C-130-08/2023] ISSUES There i
CIPAA 2012 : Can a Stay be Granted after an Adjudication Decision is enforced?
Econpile (M) Sdn Bhd v ASM Development (KL) Sdn Bhd & Anor Case [2024] 5 CLJ 16
CIPAA 2012 : Can a Stay be Granted after an Adjudication Decision is enforced? ECONPILE (M) SDN BHD V ASM DEVELOPMENT (KL) SDN BHD & ANOR CASE [2024] 5 CLJ 16 ISSUES It is not
CIPAA 2012 : Money Due Or Payable – The Over-Arching Pre-Condition for Direct Payment From Principal?
JDI Builtech (M) Sdn Bhd v Danga Jed Development Malaysia Sdn Bhd [J-02(C)(A)-1066-06/2022]
CIPAA 2012 : Money Due Or Payable – The Over Arching Pre-Condition for Direct Payment From Principal? JDI BUILTECH (M) SDN BHD V DANGA JED DEVELOPMENT MALAYSIA SDN BHD [J 02(C)(A
CIPAA 2012 : Limitation to an Adjudicator’s Jurisdiction
Anas Construction Sdn Bhd v JKP Sdn Bhd & Another Appeal [02(F)-3-01/2023(P)/ 02(F)-4-01/2023(P)]
CIPAA 2012 : Limitation to an Adjudicator’s Jurisdiction ANAS CONSTRUCTION SDN BHD V JKP SDN BHD & ANOTHER APPEAL [02(F)-3 01/2023(P) / 02(F)-4-01/2023(P)] ISSUES If an Adjud
CIPAA 2012 : Direct Payment from Principal and Judicial Management Order
Concrete Empire Sdn Bhd v Turnpike Synergy Sdn Bhd [WA-24C-116-06/2022]
CIPAA 2012 : Direct Payment from Principal and Judicial Management Order CONCRETE EMPIRE SDN BHD V TURNPIKE SYNERGY SDN BHD [WA-24C-116 06/2022] [2023] ISSUES When the losing respo
On Demand Performance Guarantee: Unconscionability and Breach of the Underlying Principle Contract
Oxley Rising Sdn. Bhd. v Ssyangyong Engineering & Construction Co. Ltd. And Anor Appeal [W-02(C)(A)-274-02/2022 & W-02(IM)(C)-273-02/2022]
On Demand Performance Guarantee: Unconscionability and Breach of the Underlying Principle Contract OXLEY RISING SDN. BHD. V SSYANGYONG ENGINEERING & CONSTRUCTION CO. LTD. AND A
CIPAA 2012 : “Adjudicated Amount” under Section 30 – Interest and Costs, Included or Otherwise?
Pali PTP Sdn Bhd v Bond M&E Sdn Bhd & Another Appeal [W-02(C)(A)-314-02/2021 / W-02(C)(A)-399-02/2021]
CIPAA 2012 : “Adjudicated Amount” under Section 30 – Interest and Costs, Included or Otherwise? PALI PTP SDN BHD V BOND M&E SDN BHD & ANOTHER APPEAL [W-02(C)(A) 314-0
CIPAA 2012 : Forbearance, Estoppel and Ouster by Contract
Chua Heng Hong & Ors v S Lite Electrical and Engineering Sdn Bhd & Anor [2023] 1 LNS 335
CIPAA 2012 : Forbearance, Estoppel and Ouster by Contract CHUA HENG HONG & ORS V S LITE ELECTRICAL AND ENGINEERING SDN BHD & ANOR [2023] 1 LNS 335 ISSUES If a party has agr
CIPAA 2012 : Setting Aside – Res Judicata & Excess of Jurisdiction. Can a new Adjudication be initiated and decided based on the same Adjudication papers?
Meridian Contracts Sdn Bhd v Bauer (Malaysia) Sdn Bhd [WA-24C-137-07/2022]
CIPAA 2012 : Setting Aside – Res Judicata & Excess of Jurisdiction. Can a new Adjudication be initiated and decided based on the same Adjudication papers? MERIDIAN CONTRACTS
Liquidated Ascertained Damages : Can a Main Contractor impose LAD on a Nominated Subcontractor when the Employer did not impose any LAD?
Pantas Alam Sdn Bhd v Hau Wah Letrik Sdn Bhd [PA-22NCvC-18-01/2022]
Liquidated Ascertained Damages : Can a Main Contractor impose LAD on a Nominated Subcontractor when the Employer did not impose any LAD? PANTAS ALAM SDN BHD V HAU WAH LETRIK SDN BH
CIPAA 2012 : Exceptional Circumstances for Conditional Stay of Adjudication Decision pending Litigation / Arbitration
Mudajaya Corporation Bhd v KWSL Builders Sdn Bhd and Anor Case [BA-24C-52-08/2022 & BA-24C-56-08/2022]
CIPAA 2012 : Exceptional Circumstances for Conditional Stay of Adjudication Decision pending Litigation / Arbitration MUDAJAYA CORPORATION BHD V KWSL BUILDERS SDN BHD AND ANOR CASE
Stay Pending Arbitration : Limitation stops when action commences in Civil Courts
SH Builder & Marketing Sdn Bhd v Bongsor Bina Sdn Bhd [2022] 1 LNS 2839
Stay Pending Arbitration : Limitation stops when action commences in Civil Courts SH BUILDER & MARKETING SDN BHD V BONGSOR BINA SDN BHD [2022] 1 LNS 2839 ISSUES When an action
Loss & Expense : “Within” and “Beyond” Reasonable Contemplation
Jabatan Kerja Raya Malaysia & Kerajaan Malaysia v Sunissa Sdn Bhd [2022] 1 LNS 1119 [Court of Appeal]
Loss & Expense : “Within” and “Beyond” Reasonable Contemplation JABATAN KERJA RAYA MALAYSIA & KERAJAAN MALAYSIA V SUNISSA SDN BHD [2022] 1 LNS 1119 [COURT OF APPEAL
CIPAA 2012: Direct Payment from Principal and the Retrospective Effect of Ireka and Jack-in-Pile cases
IT Max Engineering Sdn Bhd v Propel Synergy Sdn Bhd [2021] 1 LNS 105
CIPAA 2012 : Direct Payment from Principal and the Retrospective Effect of Ireka and Jack-in-Pile cases IT Max Engineering Sdn Bhd v Propel Synergy Sdn Bhd [2021] 1 LNS 105 ISSUES
CIPAA 2012 : Early Court Intervention and Definition of “Occupation” under Section 3
Liew Piang Voon v WLT Project Management Sdn bhd [2020] 1 LNS 1105
CIPAA 2012 : Early Court Intervention and Definition of “Occupation” under Section 3 Liew Piang Voon v WLT Project Management Sdn bhd [2020] 1 LNS 1105 Issues Section 3 of the